CASE STUDY NO 5

Client:

Trinity Academy, Nottingham

The Trinity Catholic Academy Trust

Client Requirements:

This project consisted of the replacement of a MUGA and the construction of a 23 classroom teaching block.

Budget:

£2,000,000.00

Programme:

56 weeks

Contract:

JCT Design and Build.

Challenges:

Co-ordination of the contractors activities as there were two main contractors on site; one constructed the MUGA and one constructed the teaching block