CASE STUDY NO 8

Client:

South Wilford Academy, Nottingham

Transform Trust

Client Requirements:

This project consisted of the extension of the school hall including toilet facilities.

Budget:

£300,000.00

Programme:

35 Weeks

Contract:

JCT Minor Works.

Challenges:

Manging the client’s budget. The works went through a number of value engineering processes in order to get the build cost in line with the budget.