CASE STUDY NO 2

Client:

Saint Ralph Sherwin Catholic Multi Academy Trust
St Edward’s Catholic Primary Academy. Swadlincote

Client Requirements:

This project consisted of extending and remodelling administration area, extending hall and creating central access corridor.

Budget:

£450,000.00

Programme:

Phased works comprising of four elements. Protracted programme to cater with the schools operational needs. Total no of weeks on site; 26.

Contract:

JCT Intermediate Contract.

Challenges:

Working in a live school environment in sensitive areas. We temporarily relocated the reception office and created a temporary site access. We utilised the school holidays and timed the most disruptive activities to cause as little disruption as possible.